Case Study 3

Phased Basement Car Park Smoke Clearance and Pollution Control

CFD analysis of an impulse ventilation system, demonstrating effective air movement for everyday pollution control and post-fire smoke clearance.

Project Overview & System Type

This study assessed the proposed ventilation system for the first configuration of a phased basement car park development. Mechanical extract and induction fans were used to move air through the assessed car park area, supporting both day-to-day pollution control and smoke clearance for firefighting operations.

The Engineering Challenge & Regulatory Framework

The design team needed evidence that the interim car park layout could achieve the required ventilation performance before a future extension. The assessment used the project Qualitative Design Review and relevant guidance, including Approved Documents B and F, BS 7346-7 and Smoke Control Association CFD guidance for car park ventilation.

CFD Modelling & Analysis Methodology

NIST Fire Dynamics Simulator was used to represent the car park geometry, extract arrangement, openings and induction fans. Tracer-gas decay provided a means of evaluating overall ventilation and the distribution of air movement throughout the space. The modelled fan thrust was checked against the manufacturer's low- and high-mode duties.

Simulation Scenarios & Verification Strategy

The system was assessed separately at its 6 air changes per hour pollution-control duty and its 10 air changes per hour smoke-clearance duty. Each 15-minute simulation examined the volume-mean tracer-gas decay and local removal patterns, giving the team a clear picture of ventilation performance across the modelled layout.

Results & Performance Outcomes

In the pollution-control simulation, the cumulative-average effective ventilation rate exceeded the 6 air changes per hour target and rose above 9 by the end of the simulation. In smoke-clearance mode, it exceeded the 10 air changes per hour target and rose above 14. The local tracer-gas assessment also showed effective distribution across the assessed volume under the simulated conditions.

Value Delivered & Design Implications

The study gave the project team clear, quantitative evidence for the interim ventilation arrangement. By assessing both operating duties and verifying the fan representation, the CFD analysis supported informed decisions for a phased development while demonstrating the performance of the modelled car park configuration.